What the estimate at completion is
The estimate at completion (EAC) answers one question: how much will I have spent when this project is finished? Your expected margin is the project value minus that figure.
On custom-built projects the margin is decided while the work is under way, not when the books close. Once acceptance testing is over you can only take note of how it went. The EAC shows you the problem while you can still act on it.
The four numbers you need
- Project value. The price agreed with the customer, change orders included.
- Cost budget. What you planned to spend in total: labour, materials, travel.
- Actual cost to date. Hours worked at their cost, materials received, expenses.
- Real progress. How much work is actually done, not how much budget is spent: phases completed, materials delivered and installed.
From these you get two helper numbers:
Cost performance index (CPI) = EV ÷ actual cost
A CPI above 1 means you are spending less than planned. Below 1, every euro of work is costing you more than a euro.
Three ways to calculate it
- At the current rate: EAC = budget ÷ CPI. You keep spending the way you have so far. It is the most cautious estimate, and the right one when the overrun comes from how the work is done, for example underestimated assembly hours or rework.
- Rest on budget: EAC = actual cost + (budget − EV). The overrun so far stays, the rest goes as planned. It is the optimistic estimate, and fits when the overrun was a one-off, such as a late component or a stoppage.
- Bottom-up: EAC = actual cost + cost to complete. It is the most reliable, but only if someone has really counted the remaining hours and the orders still to arrive.
A worked example
These figures are an example, not a real project. A robotic cell sold for €200,000, with a cost budget of €150,000. You have spent €90,000 so far and the work is 50% done.
| Step | Calculation | Result |
|---|---|---|
| Budgeted margin | 200,000 − 150,000 | €50,000 (25%) |
| Earned value (EV) | 150,000 × 50% | €75,000 |
| Efficiency (CPI) | 75,000 ÷ 90,000 | 0.83 |
| EAC at current rate | 150,000 ÷ 0.83 | €180,000 |
| EAC rest on budget | 90,000 + (150,000 − 75,000) | €165,000 |
| EAC bottom-up | 90,000 + 70,000 counted to complete | €160,000 |
| Expected margin | 200,000 − EAC | €20,000 – 40,000 |
The margin at quotation was 25%. At the current rate it drops to 10%; rest on budget gives 17.5%, bottom-up 20%. The three estimates are far apart, so this project needs attention now. That gap usually means the reported progress does not match the work actually done.
Using it to make decisions
- Measure progress by work done, not by money spent. Using spent budget as progress hides exactly the overruns you want to see.
- Recalculate often. On a special machinery project at least weekly, and always after an event: a late delivery, rework during testing, a customer change.
- Watch the gap between the three estimates. If they are close, the project is under control. If they are far apart, ask the person running it to count what is left.