How to calculate the estimate at completion of a project

In short

The estimate at completion (EAC) is what you will have spent when the project is finished: cost to date plus the cost to complete. There are three ways to calculate it: at the current rate (budget ÷ CPI), rest on budget (cost to date + budget − work done) and bottom-up (cost to date + counted cost to complete). Project value minus EAC gives the expected margin.

What the estimate at completion is

The estimate at completion (EAC) answers one question: how much will I have spent when this project is finished? Your expected margin is the project value minus that figure.

On custom-built projects the margin is decided while the work is under way, not when the books close. Once acceptance testing is over you can only take note of how it went. The EAC shows you the problem while you can still act on it.

The four numbers you need

  1. Project value. The price agreed with the customer, change orders included.
  2. Cost budget. What you planned to spend in total: labour, materials, travel.
  3. Actual cost to date. Hours worked at their cost, materials received, expenses.
  4. Real progress. How much work is actually done, not how much budget is spent: phases completed, materials delivered and installed.

From these you get two helper numbers:

Earned value (EV) = budget × progress
Cost performance index (CPI) = EV ÷ actual cost

A CPI above 1 means you are spending less than planned. Below 1, every euro of work is costing you more than a euro.

Three ways to calculate it

  1. At the current rate: EAC = budget ÷ CPI. You keep spending the way you have so far. It is the most cautious estimate, and the right one when the overrun comes from how the work is done, for example underestimated assembly hours or rework.
  2. Rest on budget: EAC = actual cost + (budget − EV). The overrun so far stays, the rest goes as planned. It is the optimistic estimate, and fits when the overrun was a one-off, such as a late component or a stoppage.
  3. Bottom-up: EAC = actual cost + cost to complete. It is the most reliable, but only if someone has really counted the remaining hours and the orders still to arrive.

A worked example

These figures are an example, not a real project. A robotic cell sold for €200,000, with a cost budget of €150,000. You have spent €90,000 so far and the work is 50% done.

StepCalculationResult
Budgeted margin200,000 − 150,000€50,000 (25%)
Earned value (EV)150,000 × 50%€75,000
Efficiency (CPI)75,000 ÷ 90,0000.83
EAC at current rate150,000 ÷ 0.83€180,000
EAC rest on budget90,000 + (150,000 − 75,000)€165,000
EAC bottom-up90,000 + 70,000 counted to complete€160,000
Expected margin200,000 − EAC€20,000 – 40,000

The margin at quotation was 25%. At the current rate it drops to 10%; rest on budget gives 17.5%, bottom-up 20%. The three estimates are far apart, so this project needs attention now. That gap usually means the reported progress does not match the work actually done.

Using it to make decisions

  • Measure progress by work done, not by money spent. Using spent budget as progress hides exactly the overruns you want to see.
  • Recalculate often. On a special machinery project at least weekly, and always after an event: a late delivery, rework during testing, a customer change.
  • Watch the gap between the three estimates. If they are close, the project is under control. If they are far apart, ask the person running it to count what is left.

Want to run the numbers on one of your projects? Try the free margin and EAC calculator (in Italian): the figures never leave your browser.

Frequently asked questions

Frequently asked questions

What is the EAC of a project?

It is the estimate of what the project will cost once it is finished: costs already incurred plus the cost to complete. Compared with the project value it gives the expected margin, which is what you will actually keep.

Which of the three methods should I use?

It depends on what caused the variance. If it comes from how the work is done, use the current rate; if it was a one-off event, rest on budget; if you have really counted the remaining hours and orders, bottom-up. If the three estimates are far apart, look at the project now.

What does a CPI below 1 mean?

That for every euro of work done you have spent more than a euro. With a CPI of 0.77, for example, each euro of work costs you about €1.30.

Quadra

This calculation, done automatically on every project

In Quadra cost to date adds itself up from hours clocked on the project, orders and supplier invoices. The estimate at completion updates every day, and when the margin drops below the threshold you get an alert. From 1 January 2027, registered companies can try Quadra free for 30 days on their own projects, with no credit card and direct support from the people who built it. Until then you can ask for a demo at [email protected].